Court renovation schedule

Court renovations are now officially scheduled!!!

Please note that this is our best guess of schedule and timing. Things may change depending on many factors. We’ll do our best in updating you should this schedule change.

  • Court 3 (currently Racquetball only)
    • Thursday 7/26/2012 Demolition of doorway wall and trim
    • Friday 7/27/2012 Demolition continued and complete. Floor sanding starts and completed.
    • Monday 7/30/2012 – Friday 8/3/2012 Front hit wall prep, fill, finish and paint. Side walls as needed.
    • Monday 8/6/2012 – Friday 8/10/2012 Installation of fixed glass back wall. Should be finished by Friday. Start time depending on crew availability.
    • Monday 8/13/2012 Court 3 available for play.
  • Court 4 (Flex court)
    • Monday 8/13/2012 – Monday 8/20/2012 Front hit wall prep, fill, finish and paint. Side walls as needed. Court will remain closed until 8/13/2012 to allow for materials to dry completely.
  • Courts 1 & 2 (smaller courts)
    • Minor patching of sidewalls will take place during the 2 weeks that the wall crew is working on the other courts. They expect to finish one before starting the second. Courts will need time to dry.

See our Google calendar for more information!