Renovations update

Some changes in the availability of squash courts at the Portland YMCA

Flex court front wall is taking longer than expected. It will reopen on Tuesday September 4th, 2012 The two small courts (courts 1 and 2) will close Friday morning and reopen on Tuesday September 4th, 2012

Box league for September will officially start . . . → Read More: Renovations update

New International Squash Court open for play!

Portland YMCA’s new International Squash Court is now open!

Bright, clean and brand new!

Installing the glass wall!

I caught the guys installing the glass wall today. They were hard at work making sure that our new court will have a great new glass wall.

. . . → Read More: Installing the glass wall!

Renovations update

Photos taken on Sunday

Court renovation schedule

Court renovations are now officially scheduled!!!

Please note that this is our best guess of schedule and timing. Things may change depending on many factors. We’ll do our best in updating you should this schedule change.

Court 3 (currently Racquetball only) Thursday 7/26/2012 Demolition of doorway wall and trim Friday 7/27/2012 Demolition continued and complete. . . . → Read More: Court renovation schedule